Valencia School is back in session starting 8/16.  With that, we are directing that all work on Trout Gulch begin AFTER 9am in an effort to limit any impact our project has on traffic.   Please note that we do not have permission to work nights or weekends.

Regarding Schedule, we anticipate the work on Trout Gulch and adjacent sidewalk to be complete by the end of August, with exception of final top paving to occur by early next year.

Given the previously unmapped conditions in Trout Gulch, there has been substantially more work in the area than anticipated.  Please know that Swenson and our sub-contractors are doing everything possible to complete it and are committed to maintaining safe passage for all in the interim.