SITE PREPARATION

05 Feb SITE PREPARATION

Main activities planned for week of Feb 8-12:

  • removal of old concrete footings, trash, and other debris.
  • removal of masonry shed.
  • continued erosion control.
  • grading a level area for the future site of the historic Hihn Apple Barn.
  • seeding soil areas with groundcover and native plants that were cleared but will not see additional work at this time.

 